How is PCC ratio calculated?

Suppose we have project of making concrete pavement of area 100m2 and slab thickness of PCC is 150 mm.

Now we have to calculate dry volume calculating dry volume we should multiply a cofactor 1.54 in wet volume.

Mix ratio in M15 grade = 1:2:4 one part cement two part is sand and 4 part is aggregate..

What does the PCC stand for?

Like other grocery cooperatives, the profits from the retail store operations go directly back into the stores or to the community (through classes, education or charitable efforts). PCC, originally Puget Consumers Co-op, became PCC Natural Markets in 1998 and PCC Community Markets in 2017.

What is PPC cement?

PPC Cement stands for” Portland Pozzolana Cement”. Pozzolana is an extender a supplementary cementitious material used to enhance improve the strength and durability of the cement. The word Pozzolana comes from the word ‘Pozzoluana’ which is a form of Volcanic Ash.

How do I calculate volume of 50kg cement bag?

Density = mass/volume (ρ=m/V) So, V=m/ρ 50 kg ÷ 1440 kg/m3 = 0.0347 m3 = 1.23 CFT.

How many bricks are required for 1m3?

500Ans. :- 500 no of bricks are used in 1m3 (cubic metre) of brickwork of 4 inch brick wall.

Which cement is used for PCC?

Portland cementCement: We generally use Portland cement as bonding material in PCC. Fine Aggregate: Sand is used as fine aggregate. The FM of sand should be 1.2 to 1.5. Coarse Aggregate: We normally use brick chips for producing PCC.

What is PCC concrete ratio?

Strength of PCC (Plain Cement Concrete)/Nominal Mix: The proportions of materials (cement, sand, coarse aggregate) for nominal mix/design mix concrete that are normally used are 1:3:6 or 1:4:8. As strength is not a major criterion, the design mix is generally avoided.

Why is PCC used in construction?

The main reason of providing PCC is to provide a rigid impervious bed to RCC in the foundation before starting any RCC or masonry work directly on the excavated soil, PCC is done to form a leveled surface and to avoid laying concrete on soil directly so as to avoid mixing with soil and also to prevent soil extracting …

How many bags of cement is 1m3?

Approximately 29 bags are required for 1m3 of cement.

What is PCC road construction?

Plain cement concrete is the mixture of cement, fine aggregate(sand) and coarse aggregate without steel. PCC is an important component of a building which is laid on the soil surface to avoid direct contact of reinforcement of concrete with soil and water. Fig 1: Laying of PCC.

What is the ratio of RCC?

Concrete code and concrete ratio:Concrete GradeProportion of Cement : Sand : Stone piecesExpected Compressive Strength at 28 daysM1001 : 3 : 610 N/mm2 or 100 Kg/cm2M15 or M1501 : 2 : 415 N/mm2 or 150 Kg/cm2M20 or M2001 : 1.5 : 320 N/mm2 or 200 Kg/cm2M25 or M2501 : 1 : 225 N/mm2 or 250 Kg/cm2Jan 25, 2013

What is a PCC slab?

Portland cement concrete (PCC) pavements (or rigid pavements) consist of a PCC slab that is usually supported by a granular or stabilized base, and a subbase. In some cases the PCC slab may be overlaid with a layer of asphalt concrete.

What is RCC and PCC?

Plain cement concrete (PCC) is a hardened mass obtained from a mixture of cement, sand, gravel, and water in definite proportions. … If steel is kept in the concrete then it is called Reinforced cement concrete (RCC).

How many bags of cement do I need calculator?

For concrete, the formula for volume is as follows: length x width x thickness. To determine how many bags of concrete you will need, divide the total cubic yards needed by the yield. Use the following yields per each bag size: 40 pound bag yields .011 cubic yards.

What is the ratio of concrete slab?

A concrete mix of 1 part cement : 2 parts sand : 4 parts coarse aggregate should be used for a concrete slab. Concrete must be placed within half an hour of mixing.